Thursday, February 21, 2013

Ft. Totten Square In The News

  The Washington Informer had a piece this week on the New Ft. Totten Square groundbreaking and some a few notes from community emebers and some of our local representatives in the City Council.  It's a quick and easy read that can be found here:
http://washingtoninformer.com/index.php/local/item/13084-groundbreaking-for-fort-totten-square

Friday, February 8, 2013

Ft. Totten Square/Walmart Construction Begins

So now that things have began progressing, we thought we'd provide a construction update on what is happening over at the Ft. Totten Square site.  The new year has come and gone, and the site of the District's newest Walmart has begun buzzing with workers and machinery.  JGB Group sent out a press release detailing the project, which can be found here.  As the initial dig kicks off, the sound of pile driving equipment can be heard throughout the surrounding neighborhood.  The low hum of excavators, bulldozers, and other heavy equipment fills the air.  Finally some real progress at the MUCH anticipated and LONG awaited Ft. Totten Square.

Looking SW From the Corner of 3rd & Chillum NE


Looking along the Chillum PL NE side of the site towards SD Ave.

View along the 3rd St NE Side of the Site,
South Towards the Riggs and SD Ave Intersection

View 1 Along Riggs Rd => North

View 2 Along Riggs Rd => North

View 3 Along Riggs Rd => North



Thursday, September 6, 2012

Faith United Church of Christ Proposed Retirement Home

  At last night's North Michigan Park Civic Association Meeting, the major topic of conversation was a proposed Retirement Home to be built on the grounds of the Faith United Church of Christ's property.
View Larger Map   The church is looking to sell that land to a developer (the Retirement Housing Foundation) in order to develop a 94 unit senior living community to be operated in conjunction with Faith UCC. While this is still very, very early on in the development plan, the two groups are providing initial details on their proposed project with the NMPCA and the neighborhoods residents.  Below you will find the Fact Sheet handed out las night on the project.  There are also two schedule meetings in the coming weeks to discuss the proposed plan, which all are encouraged to attend and participate in:
 September 15th
 10:00 AM to 3:00 PM
 North Michigan Park Recreation Center

 September 22nd
 10:00 AM to 3:00 PM 
 North Michigan Park Recreation Center










Wednesday, September 5, 2012

September DC Zoning Hearings of Interest and Pertainng to ANC 5A

  Here are a list of the upcoming DC Zoning Comission and Board of Zoning Adjustment hearings this month that may be of interest to our neighbors.  All hearings are held at:                               
                                                  One Judiciary Square
                                                  441 4th Street, NW
                                                  Washington, DC 2001


The full calender of the ZC and BZA can be found here.



Sept. 11 2012
9:30 AM

Case Number :18392
Case Name: Application of Betty J. Williams
Case Summary :(Special Exceptions) Pursuant to 11 DCMR § 3104.1, for a special exception under section 205 to allow a child development center (12 Children and 2 Teachers) in the R-2 District at premises 5350 Chillum Place, N.E. (Square 3751, Lots 138).

Case Number :18460
Case Name:Request for Expedited Public Hearing for Appeal No. 18460 of Ginia L. Avery, et al.
Case Summary :(Appeals) Pursuant to 11 DCMR §§ 3100 and 3101, from a decision by the Department of Consumer and Regulatory Affairs, to issue a building permit (#B1202925) allowing the construction of a Walmart store in the C-3-A District at premises 5929 Georgia Avenue, N.W. (Square 2986, Lot 38).

Sunday, June 24, 2012

DDOT Traffic Advisory For S.D Ave Final Configuration


From DDOT:
                                                          ***TRAFFIC ADVISORY***
             Temporary Closures and Final Traffic Pattern Shift Set for South Dakota Avenue, NE

  Traffic Pattern Shifts for South Dakota Ave and Riggs Rd NE (Washington, D.C.) are scheduled to finalize on June 25th. The District Department of Transportation (DDOT) will be installing the final asphalt pavement on South Dakota Avenue, NE between Riggs Road and Kennedy Street.  This activity marks the final major milestone in the completion of the Riggs Road and South Dakota Ave intersection reconstruction project in northeast Washington. While this paving activity takes place there will be intermittent lane closures and temporary traffic pattern shifts on South Dakota Avenue, NE.   At a minimum one traffic lane will be kept open in each direction at all times.  Once the pavement process is complete, traffic will be shifted into the final configuration. Variable message signs will be in place to guide motorists through the area.  Drivers and pedestrians are urged to stay alert and use caution when traveling by the work zone.
                                              ---------------------------------------------

  While the shift to the final traffic pattern means the end moving the street acesse around, it does not mean the end of construction.  However it is a good sign that the end is nearing!

Friday, June 1, 2012

New Automated Speed Enforcement Camera Locations

MPD has sent out a list of the newest automated speed enforcement camera locations across the city.  Per the MPD release, "the 30 day educational phase will commence on May 7, 2012, when violators will begin receiving warning citations. On June 6, 212, MPD will begin issuing live moving citations to violators."
See the below image for exact locations, and good luck!

Wednesday, May 23, 2012

Temporary Closure Planned for Chillum Pl NE, May 24-26

  Starting tomorrow (May 24, 2012) Chillum Place, NE will be temporarily closed south of Riggs Road, NE. Weather and construction conditions permitting, DDOT will close Chillum Place, NE south of Riggs Road, NE between 8:00 a.m. and 6:00 p.m. to connect a new water pipe to the existing system.   The same stretch of Chillum Place will close again starting at 8:00 a.m. on Friday May 25, 2012 and will reopen by 5:00 p.m. on Saturday May 26, 2012 to complete roadway excavation and concrete base installation activities. During this closure, access to the businesses on the corner of Riggs Road and Chillum Place NE will be kept open from both streets.    Signs will be in place to guide travelers in the corridor around the temporary traffic pattern.  Drivers and pedestrians are urged to stay alert and use caution when traveling by the work zone.

Tuesday, April 3, 2012

Violent Crimes and Neighborhood Watches

  Reports have recently come in of another mugging taking place in the park that seperates Galloway and Gallatain St's NE early Sunday morning, on the upper path close to the Magnolia Plumbing Facility.  An adult male was walking through the upper section of the park, and was attacked by two males with a 3' section of pipe and struck in the back.  During the altercation only his cell phone was taken, and he sustained fairly minor injuries.  Park Police are working with the victim, but this is yet another instance of neighbors being assulated or ambused (regardless of which they have definitely been targeted) while walking through the park to get home.  In the past few months there have been several robbery attempts, utilizing various weapons, in the park yet nothing seems to change.  Although there seems to be more police presence at the metro station itself, there is still a marked lack of police presence away from the station.  Many long time residents see this as a trend taking them back nearly a decade ago when violent crimes and rape were major problems in the park.  Some neighbors have commented on seeing police occasionally patrolling the paths, but acknowledge more needs to be done.   
  DDOT (d.), in partnership with Toole Design, is still in the process of finalizing their plan to improve the Metro Station and park area safety and accessibility.  Their plan to increase lighting, add new paths, better sight lines and safer sidewalks also extend to improving the paths and safety of the park access points. The d. and Toole Design Project Managers were contacted for updates on the project, but no response was received.  However, d. still broadcasts that work on this redesign will begin later this year, and cost just under $3M.  Information on the redesign and current status can be found here : http://tooledesign.com/forttotten/downloads/2011-08-04_1st-Galloway_ReportFINAL.pdf and here: http://tooledesign.com/forttotten/.
  In the interim, however, personal safety and increased vigilance is recommended.  With this in mind Samantha Nolan, Neighborhood Watch Coordinator for DC, will be holding a Community Watch Training Session at the Lamond Riggs Library on South Dakota this Thursday (April 5th).  Ms. Nolan has over 11 years experience with Community Watches and will be providing this training free of charge to all in attendance. Attendance is strongly encouraged!

Neighborhood Watch Training Session

Thursday April 5, 2012
7:00 pm - 8:30 pm
Location: Lamond-Riggs Library
Street: 5401 South Dakota Avenue, NE
City State Zip: Washington, DC 20011
Phone: 202.541.6255
Web: http://www.dclibrary.org/lamond.

Monday, April 2, 2012

Cafritz Foundation Power Ups Art Place Project

  
Rendering on new "Building B"
facing South Dakota Ave
  As many members of the community have found out, the Morris & Gwendolyn Cafritz Foundation has begun advertising Stage 1 of the Art Place project at the intersection of Galloway and South Dakota.  For many in the neighborhood this is a welcome sight of progress for a project thought by many to be dead (although if you remember correctly we have been letting you know of the accurate status of this project from day one...horray us).  With this new jolt of life, there has been some additional information coming from the DC Office of Zoning (DCOZ) and Cafritz on the other portions of this project as well. 
 
Side Elevation of Bldg B with Detail
    
Earlier this month DCOZ released the Cafritz Foundations application for modification of approved planned unit development.  In this application the Foundation sought to modify it's Phase 1 (Building A) and modify Phase 2 (Building B).   With a still sluggish economy, all would expect Cafritz to decrease the size and scope of such a large project.  However, Cafrtiz shocked everyone by increasing the size of the Phase 2, rather than decreasing it, and asking for some leeway with regards to the full service grocery planned for Building 1.  In total the requested changes featured one major (and in this life long hockey playing bloggers point of view amazingly awesome) addition, the swap out of a senior center with all age accessible ICE RINKS and recreation spaces.  Yes, you read that correctly...up to 3 sheets of ice/indoor recreation space for the community to utilize year round.  This combined recreation facility would be a major boost to the neighborhood and city in general.  Also detailed in the release were design plans for the exterior, detailed height and easement measurements, parking garage details, as well as information regarding the children's museum.  

Street level
Level 2
 "The Foundation has refined the design of Building B in terms of its mixture of uses, the functionality and efficiency of the building's layout and pedestrian and vehicular circulation, and the architectural vocabulary and materials of the building. This refinement has resulted in the addition of an exciting new use to the building - a state of the art multi-purpose recreation facility with mezzanine capable of accommodating multiple ice rinks as well as other sports playing surface - to compliment already-significant retail offerings and an innovative cultural component in the form of a children's museum."
 (Statement of the Morris and Gwendolyn Cafritz Foundation in Support of Second Stage Application, and Modification of Approved First Stage of a Planned  Unit Development - 01/17/12)


Facade of Retail Entrance
 
Facade of Children's Museum and
Rink Entrance
"The requested modification of the First Stage PUD approval includes ( 1) an increase in building height from 60 feet to 80 feet for a portion of Building B to accommodate a mezzanine level and additional clearance for the recreation component, (2) an increase in gross floor area by approximately 49,000 square feet to 505,238 square feet of gross floor area, (3) elimination of the 15,000 square foot senior center and inclusion of that floor area within the multi-purpose recreation space available to all age groups; and ( 4) flexibility to delete the grocery store if a grocery store operator cannot be secured." 
(Application for PUD Modification DCOZ Case 06-10B)

Side Elevation of Building B With Changes
     Not called out specifically in the latest Cafritz announcement is the slight change in the Second Phase layout.  Not only will the addition of the rec space/ice rinks change the layout of the building, we can now see where the children's museum will be located as well as potential location and sizes for retail.  The children's museum was moved from its previous location, consisting of one floor, on Kennedy to having it's own dedicated entrnace on Ingraham and being multi level.   Also in the latest release is the addition of a third floor roof garden, which is assumed to be accessible through the children's museum.  Cafritz has also provided renderings of potnetial exterior sidewalk and plaza elements not initially submitted.  The exterior walkways will feature green areas and whimsical mosaic pieces, inviting neighborhood members into the various offerings the development has to offer. 

 
Exterior Front Detail

Children's Museum and Ice Rink Entrance Detail


Thursday, March 29, 2012

Riggs Road Construction Update

Below you can find the Riggs Road Construction Update, with information up to date as of last week.
Overall the project still lags behind, but they are making pretty decent progress.


Tuesday, November 22, 2011

Walmart Neighborghood Partnership Initiative

  In response to public pressure, city council concerns or whatever the reasons may be, Walmart announced it's Neighborhood Partnership Initiative on their DC Website this morning.  In this announcement, Walmart announced it's intention to not only provide the District with some 1,800 permanent jobs city wide, but also increasing the District's tax revenue by some $15 million while they also "identify and create charitable partnerships during this timeline worth $21 million in critical areas of unmet needs such as hunger relief, health and wellness, education and workforce development." The major construction projects they plan to start will also utilize DC based contractors and distributors for at least 35% of work, implement transportation demand management measures for each new store (Capital Bikeshare, bus shelters, bike racks, Smart Trip, electric car charging stations), as well as "create and fund a city wide workforce development program that provides training services for DC residents, with emphasis on programs that assist low income families, minorities, veterans, at-risk yourh and formerly incarcerated residents."  Along with the proposed workforce development program, Walmart plans to focus even more keenly on creating jobs in the communities surrounding their developments through the use of hiring centers located near each site, as well as job fairs and cooperation with CCDC and Community Groups.  Several of these items address many of the major concerns people have with the Mega Box Store, however they extent to which these are carried out and how much leverage the District has to ensure these happen will not be realized until much of the planned development in near or has been copmpleted,

Wednesday, November 16, 2011

An Unexpected Tenant: Walmart Surprise in Ft. Totten

  The quiet community is an often sought after, seldom attained dynamic in any major city...and the District is no different.  The communities surrounding Ft. Totten have been one of these rare species, and are now facing extinction straight in the face.  The announcement that Wamart is moving ahead with a bold plan to open six locations in the District, one of which will anchor the Ft. Totten Square Development, will certainly usher in a new community dynamic.  The often controversial box store giant's plan will add some 1,600 jobs in the district and create almost 600 construction jobs in the process.  The Ft. Totten location will occupy most of the first floor of the Ft. Totten Square project and sit below some 350 apartments along Riggs Rd, NE. 
  Much of the community seems split regarding the planned development, and this will surely fuel the  fire for both sides.  While the neighborhood will surely be faced with all manner of city planning and public safety issues, this announcement will surely add a turbo booster to the stagnent Ft. Totten Square project and help bloster not only jobs but also increase property values.  Regardless of the stance, this unexpected announcement  looks to be moving ahead...at what speed and where the speed bumps lie are still unknown.

Friday, April 15, 2011

Ft. Totten in the News

Alot of peoiple have been worried about grim outlook of Ft. Totten in DCMud post a few weeks ago.  The post viewed Ft. Totten as a lost cause and floundering.  However, we were contacted by Andrew Siddons of Urban Turf right before the DCMud article ran, and had began talking with him on his neighborhood profile piece.  His article has finally ran, and it paints a much different picture of our quiet corner of the city.  Regardless of which position you side with, it is always interesting to see our neighborhood garnish a little attention.

Friday, March 18, 2011

Extreme Makeover: Ft. Totten Metro Station Edition

  As the construction traffic increases and multiple development projects prepare to permanently change the neighborhood landscape surrounding the Ft. Totten Metro, the residents are left pondering the question "what is being done to improve the neighborhood for us."  Well, DDOT has heard your pleas.  In fact, a little known plan has been in existence for quite some time that will totally re-invent the current pedestrian, cycle and motorized traffic patterns around the entire neighborhood.  The selected design concept for 1st Pl and Galloway St, NE will improve circulation in the area, improve the astetics of the metro station and make it more comfortable for all users going to and from the Fort Totten Metrorail Station.
  As a means of sharing this information with the neighborhood and getting your input and feedback, DDOT will be holding a meeting reviewig the proposed plan this coming Tuesday at the WMATA Police substation.  The presentation will not only review the changes to the station astetics, but also show proposed path locations (yes a cut through for the park between g\Galloway and Gallatain is in the proposal!), improved traffic signals/signage, improved lighting, improved bike storage/access and improved/additional cross walks (the below maps details areas and changes that were studied for the proposal).  If you live in the neighborhoods surrounding , or regularly use, the Ft. Totten Metrorail Station, this meeting is a must attend!



 CommunityWalk Map - 1st Place and Galloway Street NE Transportation Access Study and Improvement Plan

Ft. Totten Metro Station Transportation Access Final Project Presentation
Date: Tuesday, March 22nd, 2011
Time: 6:30 – 8:00 pm
Location: WMATA Police Substation
5315 1st Place NE
Washington DC 20011
(next to the Fort Totten Metrorail Station)
Presentation Agenda:
1. Recap of the project goals & process
2. Present preferred design
3. Discuss next steps for the design

Find out more at: http://www.tooledesign.com/forttotten

Friday, October 8, 2010

Ft. Totten Square: Finally Getting Squared Away

 The Ft. Totten Square (FTS) project has gone through many phases since it's announcement in 2006.  The once proud and highly anticipated community changing project had lost it's financial and community support, and saw a project site sit and decay for over three years.  Just when things couldn't look worse for the FTS project, the clouds parted and the sun began to shine.  Cassidy Turley Commercial Real Estate Services took on the major task of finding investors who have capitol available to refinance the project, and within months of coming on board they were able to close the refinancing deal for Lowe Enterprises.   
  For those of you that have been distracted by the massive road construction project at the intersection of Riggs and South Dakota in NE, or who haven't ventured up into this quiet section of the city, the demolition has finally begun on the former strip mall that sat on the project site. In a city feeling the economic strains shared with most of the country, the project will give a much needed economic boost to the City and Ward 5 economy.  This project will not simply create a temporary boost for blue collar jobs, but more importantly will create long term sustainable jobs in the massive mixed use project.  When we sat down with Ward 5 City Council Representative Harry Thomas last month, he noted the fact that Ward 5 job set asides are always at the top of his priority list when it comes to discussions with new commercial establishments.  Second on his list would be assisting locally owned business, especially restaurants, acquire the funding they need to gain a foothold in the new neighborhood markets. 
   While the new time line has not yet been revealed (both Lowe and Cassidy Turley had been contacted serveal times but provided no response), the future surely looks bright for the FTS project.  The coming retail and culinary additions to the neighborhood landscape will be closely followed, and hotly debated (most exciting of which could be the new full service grocery slated to anchor the retail side of the development). But only time will tell how the project pans out, and what direction the project ultimately takes.  One thing for sure is that the project is moving forward at a brisk pace, and regardless of the final product it has removed a growing eyesore from the neighborhood.

Artist's rendition of the finished Ft. Totten Square project
(Ft. Totten Metro and S.D. Ave at top right of image)